This project was an urban regeneration scheme with highways already in place. Avie ensured that the existing drainage system was improved during development to ensure that flooding did not affect any new properties.
By undertaking a Microdrainage model of the existing site drainage and fixing the existing pipe diameters, we were abel to prove, by connecting the new drainage in at less critical points in the system, that flooding was reduced on site by 76%.
Avie were successful if negotiating and agreeing the use of a combined drainage system which meant time saving and construction cost savings.